ü The tender for the supply of the solid waste collection containers (capacity 1100 liters) and waste collection vehicles (2 pick up trucks and 1 compactor 10 m3) was launched in December 2006. The bid opening session took place on 6 February 2007.
ü The containers were delivered on site by the Supplier (ALBINA) in June 2007.
ü A formal reception of the vehicles took place on 18 October 2007.Vehicles will be delivered on site after completion of the acceptance report.
ü The tender documents (including detailed design, technical specifications and Bill of quantities) for the construction of the sorting and composting facilities (capacities 15 and 9 t/d, respectively) was launched on 15 February 2007. Bid opening took place on 16 April 2007. The evaluation committee evaluated the received offers and provided its recommendations.
ü The contract for the construction of the Solid Waste Management Facility was awarded to Joseph Maalouf Establishment for Engineering & Contracting on 17 October 2007.
ü Works on Site were completed in July 2009 and the facility is became ready for operation.
ü The provisional acceptance of the facility took place on 9 December 2009 and was handed over to the municipality for operating it.
Project Summary